City of Carterville Water & Sewer Board met September 7.
Here is the agenda provided by the Board:
1. Call to Order / Roll Call
2. Minutes
3. Treasurer’s Report – August 2017
4. Recognition of Guests
5. Delinquent Accounts ( accounts - $_ _) Cutoff date 09/12/17
6. Bills for August 2017
7. Water Loss – August 2017 Sold 13,486,520_ Gallons
8. Garry Wiggs Report
Electronic Water Meters – Update- Bid Review
Equipment - Update – Bid Review
CDL - Update
9. Jerry Hampton Report
10. Marc Buatte Report (Sewer)
Kamper Supply Lift Station – Update
Rebuild/New Rotors for Aeration Basin at the plant-Update
Lining of 5 Manholes - $10,630.00 waiting until September 2017
11. Leak Credits and Pool Credits
12. Crawford & Associates
Sewer Plant Study – In Process – last option (Orbal & Clarifier)
Invoice for Work Completed - $17,000.00
13 2013 Water Study – Grant Applicaton –
Grant application details
Engineering Agreement
14. Water Tank Repairs – Update
Work starting Sept 5th.
15. Rend Lake Transmission Line – Update
16. Replacement of Glass Front Doors – Update
17. Water Laborer Position
18. Sewer Line Extension – Pin Oak Road
Executive Session Personnel, Possible Litigation, Possible Sale of Bonds, Possible Acquisition of Property
https://visitcarterville.com/sites/default/files/WS%20BOARD%20AGENDA%20SEPT%207%2C%202017_0.pdf