Carterville Water and Sewer Board met Thursday, Dec. 8.
"City of Carterville Water & Sewer Board is located at 101 S Division St, Carterville, IL, 62918."
Minutes of the regular meeting of the Carterville Water and Sewer Board meeting held
Thursday, December 8, 2016 at 6:00 p.m. in the Water and Sewer Department Conference Room.
Present at the meeting were: Mark Bollmann and Matt Crain, Water and Sewer Board
Commissioners; Brad Robinson, Mayor; Curt Oetjen, Council Representative; Garry Wiggs, Public
Works Director; Michael Resczenski, Water Supervisor; Marc Buatte, WWTP II Operator; Ron
Modglin and John Crawford, Crawford and Associates; Janice McConnaughy, HR Specialist; and
Mickey Edwards, Secretary.
Delinquent accounts were discussed (105 accounts delinquent in the amount of
$8,148.28). We usual shut off approximately 60-90 customers each month.
The Rend Lake bill for November 2016 was not available for the meeting. We sold
11,674,760 gallons and will determine our loss when the bill comes in.
Motion 1: Crain moved and Bollmann seconded to approve the minutes of the
November 3, 2016 Regular Meeting as submitted by the Secretary. All voted yea and the Secretary
declared the motion carried.
Motion 2: Crain moved and Bollman seconded to approve the Treasurer’s Report for the
month of November 2016. A roll call vote was taken, and all present voted yea. The Secretary
declared the motion carried.
Motion 3: Bollmann moved and Crain seconded to approve payment of the monthly bills as
submitted by the Secretary. A roll call vote was taken, and all present voted yea. The Secretary
declared the motion carried.
Mickey Edwards reported that John Geiselman is very ill and could use some company and
encouragement.
Garry Wiggs explained that there are two local communities who have electronic meters.
Garry and Amy will visit these communities and talk to their representatives about the programs that
they are using and the equipment that was installed. Garry reported that we have no safe equipment
for the Water and Sewer Department so he is interested in looking into a lease/purchase of a new
trachoe and the purchase of a used dump truck. Bud Edwards and Garry Wiggs are looking for a
used 2 Ton truck for the Sewer Department. The Board agreed to have Garry Wiggs solicit pricing for
new vehicles and equipment. Garry is working with Rodney at Crawford’s Office regarding the
renovation of the water towers.
Michael Resczenksi, Water Supervisor, reported that there were two leaks and they have
been working on hydrants and meters. Woods on DewMaine was having trouble with high usage
and Mike and Jerry found his problem and he will submit repair bills for a leak credit.
Marc Buatte, Wastewater Treatment Operator, reported that he is in the process of rebuilding
the effluent pump station and influent pump station. He and Rodney have been working with two
companies on aeration system for the oxidation ditches and should have something next meeting.
Carterville Water and Sewer Board
December 8, 2016
Page 2
The Pea Ridge Lift Station estimates for new pumps are as follows:
Municipal Equipment (ABS Pumps) $14,488.04 (2 pumps, guide rails, bases & hatch)
Vandevanter (SLYGT Pumps) $16,996.00 (2 pumps and guide rails)
Municipal Equipment (Vaughan Pumps) $26,130.60 (2 pumps guide rails, bases & hatch)
The labor cost estimates were:
Jeff Wiggs $3,090.00
Scott Escue $4,500.00
SpectreTec gave Marc a price for lining of the wet well and valve vault at $23,000.00 ($16,500.00
for the wet well and $6,500.00 for the valve vault). A new vault and wet well estimated cost is
$50,000.00 to $100,000.00. This project will have to be bid because it is over $20,000.00 unless they
price the valve vault and the wet well are bid separately.
John Crawford suggested that we try to obtain a DCEO grant for this renovation. Crawford will
get a price for replacement of the entire lift station and we will discuss this again in January, 2017.
Marc Buatte will get an additional pump price from Hydromatic.
KPS Inc. will be completing the sewer lining on Willow/Texas and the final price came in at
$16,010.00.
Marc Buatte suggested to the Board that we purchase 200 additional blocks for the Sludge
Building drying beds. The cost is $29.00 each and a pallet would be approximately $7,000.00.
Motion 4: Bollmann moved and Crain seconded to authorize Marc Buatte to purchase a
pallet of blocks for our drying beds at a cost not to exceed $7,000.00. A roll call vote was taken,
and all present voted yea. The Secretary declared the motion carried.
Motion 5: Bollmann moved and Crain seconded to approve the following leak credits:
#01-1413 Victor & Debbie Schooley, 900 E. Illinois $ 26.51
#10-0202 Hunter Abate-Barrett, 215 E. Grand Avenue $ 73.99
#10-4991 Martin Tregoning, 206 S. Carter Street $157.37
#14-0461 Evelyn Knoob, 801 Woodland Drive $ 97.98
#14-0950 Larry Hunter, 12284 Hunter Drive $ 29.25
#14-2361 Michael Allsbrook, 12401 Birch Lane $ 35.12
#14-4351 Jennifer Spence, 900 N. Division Street $130.00
$21-1961 Robert Foster, 113 Twin Lakes Road $ 55.18 $605.40
A roll call vote was taken, and all present voted yea. The Secretary declared the motion carried.
John Crawford, Crawford and Associates, presented Change Order No. 1 for an increase of
$6,340.00 on the West Grand Phase II waterline to Dean Bush Construction. John Crawford stated
that he did not include one of the mains that had to be tapped with this new line.
Carterville Water and Sewer Board
December 8, 2016
Page 3
Motion 6: Crain moved and Bollmann seconded to approve Change Order No. 1 for Dean
Bush Construction for an increase of $6,340.00 on the West Grand Phase II waterline relocation. A
roll call vote was taken, and all present voted yea. The Secretary declared the motion carried.
Motion 7: Crain moved and Bollmann seconded to approve the following bills for the West
Grand Phase II Waterline Relocation:
Dean Bush Construction Pay Estimate 2 $50,220.00
Crawford & Associates Resident Engineering $ 200.00
A roll call vote was taken, and all present voted yea. The Secretary declared the motion carried.
The downtown waterline is still pending completion of the West Grand Phase II waterline
relocation. The aeration diffusers being donated by Charleston will be picked up next week by
Rodney and Marc and they will deliver the UV Disinfection System plans.
Motion 8: Crain moved and Bollmann seconded to approve payment of the engineering
design bill on the Willow/Texas sewer lining to Crawford and Associates $1,500.00. A roll call vote
was taken, and all present voted yea. The Secretary declared the motion carried.
The Sludge Holding Structure has been changed and resubmitted to IEPA for change to the
wastewater treatment plant old drying beds.
The Water Study that has been in process with Crawford and Associates on hydrants, valves,
lines, etc. Crawford submitted preliminary drawings showing locations of hydrants, valves and lines
but this is not complete.
The Refuge meter was discussed and Mike Resczenski asked if we could replace this
compound meter with a 2” meter. We will have to get this approved by the Refuge. They have not
repaid the City for this line and meter as yet. Rodney is investigating this possibility. We will install a
backflow preventer in this meter well for the low side and bill U. S. Fish and Wildlife for this $2,600.00.
Crawford presented information regarding the relocation of our service line from Rend Lake
Intercity Water District. Ron Modglin and Rodney Potts prepared a drawing and a letter asking for
this change in our service line. The Mayor and John Crawford suggested that we contact Rend Lake
and ask them to construct this line to alleviate water breaks that we have experienced in the past.
Motion 9: Crain moved and Bollmann seconded to advertise for bids for mowing at the
water and sewer property. All voted yea and the Secretary declared the motion carried.
Motion 10: Crain moved and Bollmann seconded to pay the damage bill to AMEREN
C.I.P.S. for the damages to the gas line on the corner of Mulberry and West Grand Avenue at a cost
of $483.70. A roll call vote was taken, and all present voted yea. The Secretary declared the motion
carried.
Carterville Water and Sewer Board
December 8, 2016
Page 4
Marc Buatte and Ron Modglin televised a collection line at 605 Crab Orchard Drive and
found some problems in the line that is causing problems for a customer in this area. This collection
line was installed before sewer was available in this area and has been revised in the past. Mike
Resczenski indicated that it was also revised when Greenbriar Road was widened. There are a lot of
utility lines in this area. Marc Buatte suggested that if we repair this we need to specify that this is a
problem with a collection line that is not the City’s responsibility. This is not a sewer main and,
therefore, is not our responsibility. The Mayor indicated that we should present this video to the
customer and suggest she use this to hire a plumber.
There was a discussion of Ordinance No. 1366-14, BACKFLOW PREVENTION ON
SANITARY SEWER. This ordinance is too general and should be revised. Marc Buatte called the
State Plumbing Inspector for rewording of this ordinance. He will present this wording at the January,
2017 meeting.
There was a discussion regarding an increase in meter deposits from $75.00 to $100.00.
Amy gave some examples of this shortfall in deposits before the meeting and we are no longer
allowing landlords to
Motion 11: Crain moved and Bollmann seconded to increase the water meter deposit to
$100.00 effective by ordinance in January 2017. All voted yea and the Secretary declared the motion
carried.
Motion 12: Crain moved and Bollmann seconded to advertise for a Billing Clerk to replace
Lesa Hafford’s duties (Lesa Hafford will be doing the Accounts Receivable job and Amy Simpson will be doing
all the bookkeeping for the City and Water and Sewer Department). A roll call vote was taken, and all
present voted yea. The Secretary declared the motion carried.
Motion13: Crain moved and Bollmann seconded to change the January 2017 meeting to
Monday, January 9, 2017 at 6:00 p.m. All voted yea and the Secretary declared the motion carried.
Motion 14: Crain moved and Bollmann seconded to adjourn. All voted yea and the meeting
was dismissed at 7:28 p.m.