Quantcast

Carbondale Reporter

Tuesday, April 23, 2024

DeSoto Water Committee discusses Phase II of the watermain replacement project

Shutterstock 210286771

DeSoto Water Committee met Wednesday, March 29.

Here are the minutes as provided by the committee:

STATE OF ILLINOIS

COUNTY OF JACKSON

VILLAGE OF DESOTO

Minutes

Park Committee

March 29, 2017

The Water Committee met March 29, 2017 at 3:30 PM. The purpose of the meeting was to discuss Phase II of the Watermain Replacement Project. Chairman Larry White convened the meeting at 3:30 PM.

Present:

John Evans, Village President

Larry White, Chair

Tony Rushing, Trustee

David Griffin, Director of Public Works

Amanda Tinsley, J. T. Blankenship Inc.

Harold Sheffer, J. T. Blankenship Inc.

Dale Jones, Former Director of Public Works

Since the Village’s application for a DCEO grant to help with the project was denied, the Village will continue with the IEPA loan for the full amount. Blankinship’s preliminary estimate of the cost is $631,890.00. Amanda Tinsley and Harold Sheffer are relatively certain that the Village will get the 50% debt forgiveness. However, verification will not come until after the project has started.

Everyone reviewed the plans for Phase II. Mrs. Tinsley will get an enlarged copy of the Phase II plan sheet.

Mr. Sheffer stated that it is important to get the project started in IEPA’s current fiscal year so that this fiscal year’s funds can be used in order to get the debt forgiveness. Therefore, Mr. Sheffer would like to take bids on May 1, 2017.

The meeting ended at 4:45 PM.

Respectfully submitted,

Paula J. Parks

Village Clerk

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS